Cutting RA bill certification from four days to under an hour

Client: An infrastructure contractor operating across South India

Product deployed: ConstrakERP360

Summary

An infrastructure contractor running several concurrent sites was losing days per subcontractor to running account bill disputes. Moving measurement submission into a partner portal, with retention and advance recovery calculated automatically, reduced certification from around four days to under an hour.

Measured results

4 days → <1 hr
RA bill certification time
At indent
BOQ overruns now flagged
Per project
equipment cost allocation
Live
project profitability visibility

The challenge

The contractor ran several concurrent sites with a large subcontractor base. Each running account bill arrived as a paper measurement sheet, was re-keyed by a site clerk, checked against a spreadsheet of previously certified quantities, and then argued over.

The arguments were rarely about whether work had been done. They were about carry-forward quantities, retention percentages and advance recovery schedules — arithmetic that both sides were doing separately and getting differently.

Separately, BOQ overruns were surfacing only when invoices were booked, weeks after the material had already been consumed on site.

What we built

ConstrakERP360 was deployed with the BOQ imported per project and budgeted cost set against each line. Site indents were moved into the system, with a budget check at the point of raising: a request that would push a BOQ line past its budgeted quantity is flagged immediately rather than discovered at invoice booking.

The partner self-service portal was opened to subcontractors, who now submit measurements directly. Retention at the contracted percentage, mobilisation advance recovery on the agreed schedule, previously certified carry-forward and TDS are all computed by the system from the contract terms.

Equipment cost — owned and hired plant, running hours, fuel and maintenance — was allocated to the project that used the machine rather than absorbed into overheads, which changed several project margins materially once visible.

Site attendance moved to digital muster feeding wage computation for daily and piece-rate labour.

Our RA bill certification used to take four days of back-and-forth with each subcontractor. It now takes about an hour. The retention and advance recovery calculate themselves, so there is nothing left to dispute.
Project Controller, Infrastructure company, Chennai

Answers

Questions about this project

Did subcontractors adopt the portal willingly?

Mostly yes, once they realised it got them paid faster. The ones who resisted were given a short transition period during which site staff entered measurements on their behalf. Faster certification turned out to be a stronger argument than any mandate.

How long did the rollout take?

About ten weeks, phased by site rather than switched over at once. BOQ import and contract terms configuration took longer than the software setup.

Did they keep using Tally?

Yes. Two-way Tally integration was retained so statutory filing continued unchanged while procurement, subcontract billing and project costing moved into the ERP.

Could this work for your operation?

Bring us your numbers and we will tell you honestly whether the same approach applies.

Talk to a consultant

Prefer to talk? +91 94897 49361

Book a free demo

Tell us how you operate today and we will configure the demo around your own numbers — a weighbridge slip, a BOQ or a stock register — rather than a canned dataset.

We use your details only to respond to this enquiry. No newsletters unless you ask.